Wood Road School Complex Improvements

  • Summer of 2016: Final Phase of site work

    The former Milton Terrace school building was removed and the new parking lot/bus loop was started during the winter of 2015-16. During the summer of 2016 the final site work will be completed, including the new bus loop, parking lot, and traffic patterns. Please see the photos or the drawing attached below for an idea of what is being completed during the summer of 2016.

    Summer of 2015:

    The second phase of renovations at Milton Terrace Elementary School was completed in the summer of 2014 and phase three will be completed during the summer of 2015.

    The Wood Road Elementary School relocated to the former Milton Terrace South building for the 2014-15 school year and has moved back into the refurbished building (June 2015), including renovations to classrooms, flooring, mechanical systems and bathrooms.

    A grand reopening will be held on September 2, 2015 at the complex – watch for details as September arrives. Classes begin September 8, 2015 for all students in the BSCSD.

    The final phase of the project will then begin with the removal of the former Milton Terrace South school building and the construction of a bus loop, parking lot and new roadways during 2015-2016.